Estimating Time, Cost, and Resource Requirements

Before you can estimate duration, you need to make sure everyone is working from a common definition. The duration of a project is the elapsed time in business working days required to complete the project, activity, or task. Duration is different from effort. Effort is labor hours required to complete a project, activity, or task. Effort is always less than or equal to duration. Labor hours can be consecutive or nonconsecutive hours. It is this elapsed time that you are interested in estimating for each task. It is the true duration of the task. For costing purposes you are interested in the labor time (work) actually spent on the task.

Resource Loading versus Task Duration

The duration of a task is affected by the number of resources scheduled to work on it. I say affected by because there is not necessarily a direct linear relationship between the amount of resource assigned to a task and its duration. For example, suppose you are responsible for completing a certain programming task. You estimate that it will take 4 weeks to complete. The project manager says that it must be done in 2 weeks so she will ask another programmer to join you in the task. Will that reduce the task duration to 2 weeks? Absolutely not. There are several reasons why the relationship is not linear. Among the reasons are the need for person-to-person communications, deciding on programming conventions, deciding who will work on what, and a host of other ...

Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.

Read now

Unlock full access

More than 5,000 organizations count on O’Reilly

AirBnbBlueOriginElectronic ArtsHomeDepotNasdaqRakutenTata Consultancy Services

QuotationMarkO’Reilly covers everything we've got, with content to help us build a world-class technology community, upgrade the capabilities and competencies of our teams, and improve overall team performance as well as their engagement.
Julian F.
Head of Cybersecurity
QuotationMarkI wanted to learn C and C++, but it didn't click for me until I picked up an O'Reilly book. When I went on the O’Reilly platform, I was astonished to find all the books there, plus live events and sandboxes so you could play around with the technology.
Addison B.
Field Engineer
QuotationMarkI’ve been on the O’Reilly platform for more than eight years. I use a couple of learning platforms, but I'm on O'Reilly more than anybody else. When you're there, you start learning. I'm never disappointed.
Amir M.
Data Platform Tech Lead
QuotationMarkI'm always learning. So when I got on to O'Reilly, I was like a kid in a candy store. There are playlists. There are answers. There's on-demand training. It's worth its weight in gold, in terms of what it allows me to do.
Mark W.
Embedded Software Engineer

You might also like

Applied Software Project Management

Applied Software Project Management

Andrew Stellman, Jennifer Greene

Publisher Resources

ISBN: 9780764596360Purchase book