Let's take the actions required for this implementation and determine relations between them, estimation of time, and when they should be performed. In the example, we will not be determining the due date and the people responsible for the action.
The estimation of time will depend upon the number of fixed assets the company implementing this functionality may have:
- Get a list of fixed assets:
- When: Before the implementation
- Estimation of time: Two days
- Previous action: None
- Check the existing FA Posting Groups. Modify the existing FA Posting Groups if they do not meet your accounting requirements, or create new ones if you need to:
- When: Before the implementation
- Estimation of time: Half a day
- Previous action: None