Project uses the tracking information you provide to adjust both the schedule and the project’s costs. If Project determines that you’re running late on a task, Project moves dependent tasks into the future. And Project adjusts projected total costs using a combination of actual costs and remaining estimates.
Before you start recording tracking information in Project, you should set the status date and check your calculation options.