Resource Negotiations: A Communication Scenario

A project manager (P) and/or appropriate task leader(s) meet with a resource manager (R). They negotiate the availability of skilled persons who are managed by R and are necessary in the execution of Project X.

STEP 1.
P familiarizes R with Project X and with P's perception of its significance and priority with in the company.
STEP 2.
P seeks to understand the various activities/commitments of R's staff during the life of Project X.
STEP 3.
P shares with R the project Gantt chart (with persons from R's group who are participating) and identifies the ideal time commitment, both duration and effort, for persons on R's staff.
STEP 4.
P and R discuss the necessary tradeoffs that will enable R's ...