Integration setup in the test system

  • Purpose: The purpose of this deliverable is to set up the integration in a quality assurance system so that productions, like data, can be loaded for testing. Once testing is done in the QA system, integration will be set up in the production environment.
  • Approach: Cloud.
  • Deliverable(s): Integration is set up in the test/Q system and integration is set up in the production system.
  • Tasks summary:
    • Configure integration setup on the cloud system
    • Create integration mapping and transformation
    • Configure integration setup on the system to be integrated
    • Either in cutover or here (optional), integrate initial data load into the production system
    • Once tested, repeat the setup process in the production environment ...