Appendix

Glossary

activity:
Also known as task, an individual step performed to reach a project’s goal.
actual:
Final reporting data for a task, such as the date when the task really started versus its planned start date or the amount of work completed versus the planned amount of work.
ACWP (actual cost of work performed):
Cost of the actual, real work done on a task, work package, or project to date.
ALAP (as late as possible):
A constraint put on a task’s timing to make the task occur as late as possible in the project schedule, taking into account any dependency relationships.
analogous estimate:
An estimating method that uses information from past similar projects and tailors it for the current project estimates.
ASAP (as soon as possible):
A constraint put on a task’s timing to make the task occur as early as possible in the project schedule, taking into account any dependency relationships. This is the default constraint type.
auto scheduled:
A task mode where Project calculates the schedule as needed based on task dependencies, constraints, calendars, and resource availability.
BAC (budget at completion):
The sum total of all costs involved in completing a task, work package, or project. See also baseline cost.
Backstage view:
The area that presents files and options when you click the File tab on the Ribbon.
baseline:
The formally agreed-upon dates for start, finish, duration, work, and cost data in the project. Later, actual schedule and duration, work, and cost data ...

Get Microsoft Project 2019 For Dummies now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.