Appendix D: Sample Project Work Plan
Task |
Duration |
Start Date |
End Date |
Certify ABC System |
52 days |
10-Nov-13 |
9-Jan-14 |
Project preparation |
2 days |
10-Nov-13 |
11-Nov-13 |
Coordinate project with system owner |
1 day |
10-Nov-13 |
10-Nov-13 |
Obtain system inventory information |
2 days |
10-Nov-13 |
11-Nov-13 |
Set up project directory |
1 day |
10-Nov-13 |
10-Nov-13 |
Develop project plan |
0 days |
11-Nov-13 |
11-Nov-13 |
Project kickoff |
5 days |
11-Nov-13 |
17-Nov-13 |
Schedule kickoff briefing |
2 days |
11-Nov-13 |
12-Nov-13 |
Prepare kickoff briefing |
1 day |
12-Nov-13 |
12-Nov-13 |
Present kickoff briefing |
1 day |
17-Nov-13 |
17-Nov-13 |
Update project plan |
0 days |