Production planning 505
There are two kinds of production planning which correspond to different time spans
(Couzens, 1979):
– Operational or short-range production planning is necessary for the function of an
operating mine.
– Long-range production planning is usually done for feasibility or budget studies. It
supplements pit design and reserve estimation work and is an important element in the
decision making process.
Couzens (1979) has provided some very useful advice which should be firmly kept in
mind by those involved in the longer term planning activities:
How would I plan this if I had to be the mine superintendent and actually make it work?
In guiding the planner, Couzens (1979) has proposed the following five planning
‘commandments’ or rules:
1. We must keep our objectives clearly defined while realizing that we are dealing with
estimates of grade, projections of geology, and guesses about economics. We must be open
to change.
2. We must communicate. If planning is not clear to those who must make decisions and
to those who must execute plans, then the planning will be either misunderstood or ignored.
3. We must remember that we are dealing with volumes of earth that must be moved in
sequence. Geometry is as important to a planner as is arithmetic.
4. We must remember that we are dealing with time. Volumes must be moved in time to
realize our production goals. The productive use of time will determine efficiency and cost
effectiveness.
5. We must seek acceptance of our plans such that they become the company’s goals and
not just the planner’s ideas.
This chapter will focus on the longer term planning aspects both during feasibility studies
and later production.
6.2 SOME BASIC MINE LIFE – PLANT SIZE CONCEPTS
To introduce this very important topic, an example problem will be considered. Assume
that a copper orebody has been thoroughly drilled out and a grade block model constructed.
Table 6.1 presents an initial estimate for the costs and recoveries.
Since they will be refined later, this step will be called Assumption 1.
The best estimate price (in this case $1/lb) is also selected (Assumption 2). From these
values an economic block model is constructed. The break-even grade for final pit limit
Table 6.1. Costs used to generate the
economic block model.
Mining cost (ore) =$1.00/ton
Mining cost (waste) =$1.00/ton
Milling cost =$2.80/ton
G&A cost (mining) =$0.17/ton
G&A cost (milling) =$0.40/ton ore
Smelting, refining and sales =$0.30/lb Cu
Overall metal recovery =$78%