CHAPTER 13
Machine availability and utilization
13.1 INTRODUCTION
Today the basic method of equipment scheduling in the surface mining industry is to deter-
mine the equipment required to maintain the desired tonnage and to then schedule only the
required equipment to do the job. In the event of a breakdown, production is maintained by
the crew picking up another machine on standby or just out of repair. In order to properly
schedule and size the overall equipment fleet, knowledge of a number of factors dealing with
machine availability and utilization are needed. In this regard, one or more of the following
terms are used:
availability
operational availability
mechanical availability
physical availability
utilization
use of availability
working efficiency
job efficiency
operating efficiency
effective utilization
The calculation of useful hours or minutes is accomplished by applying these factors to
various periods of time. Time expressions such as
scheduled hours
annual hours
total hours
working hours
shift hours
operating hours
efficiency hours
may be used. Unfortunately there is little consistency with which most of these terms are
used and their values calculated in the mining industry today. Availability’ to one mining
company may not have the same meaning to another mining company or to a supplier of
mining equipment. In this section, the authors have attempted to provide a consistent set
of definitions and formulate an overall logical framework for these important concepts.
972
Machine availability and utilization 973
A number of different information sources have been drawn upon in this effort and some
new terms have been applied. It is hoped that confusion will be reduced rather than increased
with this approach.
13.2 TIME FLOW
A simple flow sheet showing the distribution of total hours for equipment at a mining
operation is shown in Figure 13.1.
The definition of the terms is given in Table 13.1.
The time flow sheet in Figure 13.1 can be represented as a series of nodes (Figure 13.2)
at which the flows are split into basically productive and non-productive streams from a
production viewpoint.
The ratio of the productive flow out of a node to the total flow into the node can be
considered an ‘efficiency ratio’ or a ‘node efficiency’. The total time flow to any given point
can then be determined by multiplying the flow in by the efficiencies of the nodes in between.
Node 1:
operational availability =
up-time
total time
(13.1)
Node 1*:
mechanical availability =
working hours
working hours + downtime
(13.2)
Figure 13.1. Total hour distribution with respect to mining machinery. Source unknown.

Get Open Pit Mine Planning and Design, Two Volume Set & CD-ROM Pack, Third Edition, 3rd Edition now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.