The following table identifies the steps, time, and immediate predecessors:
Steps | Time in Seconds | Immediate Predecessors |
---|---|---|
T 1 | 12 | None |
T 2, Type A | 13 | T 1 |
T 3 a | 14 | T 2 |
T 3 b | 10 | T 2 |
T 3-c | 11 | T 2 |
T 4 | 18 | T 3 b |
T 5, Type B | 15 | T 1 |
T 6 | 22 | T 5 |
T 7 | 10 | T 4, T 6 |