The data from the table are as follows:

Inputs.

Inputs 1 2 3 4 5 6 Total
Forecasted demand 24 142 220 180 136 168 870
Workforce level 120 158 158 158 158 158 910
Undertime 6 0 0 0 0 0 6
Overtime 0 0 0 0 0 0 0
Vacation time 20 6 0 0 4 10 40
Subcontracting time 0 0 0 0 0 6 6
Backorders 0 0 0 4 0 0 4

Derived.

Derived 1 2 3 4 5 6 Total
Utilized time 94 152 158 158 154 148 864
Inventory 70 80 18 0 14 0 182
Hires 0 38 0 0 0 0 38
Layoffs 0 0 0 0 0 0 0

Calculated.

Calculated. 1 2 3 4 5 6 Total
Utilized time cost $376,000 $608,000 $632,000 $632,000 $616,000 $592,000 $3,456,000
Undertime cost $24,000 $0 $0 $0 $0 $0 $24,000
Overtime cost $0 $0 $0 $0 $0 $0 $0
Vacation time cost $80,000 $24,000 $0 $0 $16,000 ...