Long description

The data from the table are as follows:

Inputs.

Inputs 1 2 3 4 Total
Forecasted demand 35 30 50 20 135
Workforce level 35 30 50 20 135
Undertime 0 0 0 0 0
Overtime 0 0 0 0 0

Derived.

Derived 1 2 3 4 Total
Utilized time 35 30 50 20 135
Hires 0 0 20 0 20
Layoffs 5 5 0 30 40

Calculated.

Calculated 1 2 3 4 Total
Utilized time cost $210,000 $180,000 $300,000 $120,000 $810,000
Undertime cost $0 $0 $0 $0 $0
Overtime cost $0 $0 $0 $0 $0
Hiring cost $0 $0 $160,000 $0 $160,000
Layoff cost $10,000 $10,000 $0 $60,000 $80,000
Total cost $220,000 10,000 460,000 180,000 $1,050,000