Data is as follows. Item, a. Order policy, 50 units. Lead time, 1 week. Quantity on hand, 5. Time frame displayed, 10 weeks total. Forecast. Weeks 1 8 and 10, 20. Weeks 2 and 4, 10. Week 7, 30. Week 9, 40. Customer orders booked. Week 1, 30. Week 2, 20. Week 3, 5. Week 4, 8. Week 6, 2. Projected on hand inventory. Week 1, 25. M P S quantity. Week 1, 50. M P S start. None. Available to promise, a t p, inventory, None.