Long description

The diagram shows activities A through K along with their activity times, following the sequence described in the Example 7.1 table, with the exception that Activity J is to be completed in 1 week. The critical path highlighted is from start, B, D, H, J, K, and to finish. The data from the diagram are tabulated as follows:

Activity Time
A 12
B 9
C 10
D 10
E 24
F 10
G 35
H 40
I 15
J 1
K 6