The diagram shows activities A through K along with their activity times, following the sequence described in the Example 7.1 table, with the exception that Activity J is to be completed in 1 week. The critical path highlighted is from start, B, D, H, J, K, and to finish. The data from the diagram are tabulated as follows:
| Activity | Time |
|---|---|
| A | 12 |
| B | 9 |
| C | 10 |
| D | 10 |
| E | 24 |
| F | 10 |
| G | 35 |
| H | 40 |
| I | 15 |
| J | 1 |
| K | 6 |