Long description

The diagram shows activities A through K along with their activity times, following the sequence described in the Example 7.1 table, with the exception that Activity J is to be completed in 1 week. The critical path highlighted is from start, B, D, H, J, K, and to finish. The data from the diagram are tabulated as follows:

Activity Time
A 12
B 9
C 10
D 10
E 24
F 10
G 35
H 40
I 15
J 1
K 6

Get Operations Management: Processes and Supply Chains, 12th Edition now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.