The diagram shows activities A through K along with their activity times, following the sequence described in the Example 7.1 table, with the exception that Activity D is to be completed in 8 weeks, Activity J in 1 week, and Activity K in 5 weeks. Two critical paths are highlighted: Start, B, D, H, J, K, Finish, and Start, A, C, G, J, K, Finish. The data from the diagram are tabulated as follows:
Activity | Time |
---|---|
A | 12 |
B | 9 |
C | 10 |
D | 8 |
E | 24 |
F | 10 |
G | 35 |
H | 40 |
I | 15 |
J | 1 |
K | 5 |