Long description

The diagram shows activities A through K along with their activity times, following the sequence described in the Example 7.1 table, with the exception that Activity D is to be completed in 8 weeks, Activity J in 1 week, and Activity K in 5 weeks. Two critical paths are highlighted: Start, B, D, H, J, K, Finish, and Start, A, C, G, J, K, Finish. The data from the diagram are tabulated as follows:

Activity Time
A 12
B 9
C 10
D 8
E 24
F 10
G 35
H 40
I 15
J 1
K 5