Key Equations

Performance Measures for Scheduling Processes

  1. Performance measures:

    Flow time = Finish time + Time since the job arrived at the workstation Past due = Time by which a job missed its due date Makespan = Time of completion of last job  Starting time of the first job Total inventory = Scheduled receipts for all items + On-hand inventories of all items

Job Shop Scheduling

  1. Critical ratio:

    CR= Due dateToday's date Total shop time remaining

  2. Slack per remaining operations:

    S/RO= ( Due dateToday's date )Total shop time remaining Number of operations remaining