Section 3

Project Time Management

1 QUESTION

Project Time Management comprises which seven major processes?

ANSWER

  • Plan Schedule Management
  • Define Activities
  • Sequence Activities
  • Estimate Activity Resources
  • Estimate Activity Durations
  • Develop Schedule
  • Control Schedule

[Planning and Monitoring and Controlling]

2 QUESTION

Define total float.

ANSWER

The amount of time that an activity can be delayed from its early start without delaying the project end date or violating a schedule constraint.

[Planning]

3 QUESTION

Why is the key benefit of the plan schedule management process?

ANSWER

To provide guidance and direction on how the project schedule will be managed throughout the project

[Planning]

4 QUESTION

How are performance reviews used in control ...