Section 3
Project Time Management
1 QUESTION
Project Time Management comprises which seven major processes?
ANSWER
- Plan Schedule Management
- Define Activities
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Develop Schedule
- Control Schedule
[Planning and Monitoring and Controlling]
2 QUESTION
Define total float.
ANSWER
The amount of time that an activity can be delayed from its early start without delaying the project end date or violating a schedule constraint.
[Planning]
3 QUESTION
Why is the key benefit of the plan schedule management process?
ANSWER
To provide guidance and direction on how the project schedule will be managed throughout the project
[Planning]
4 QUESTION
How are performance reviews used in control ...