1 QUESTION
Project Human Resource Management comprises which four processes?
ANSWER
- Plan Human Resource Management
- Acquire Project Team
- Develop Project Team
- Manage Project Team
[Planning and Executing]
2 QUESTION
What are two key items in managing and leading the project team?
ANSWER
- Influencing the team
- Professional and ethical behavior
[Planning and Executing]
3 QUESTION
One way to resolve conflict is through collaboration. Why?
ANSWER
It incorporates multiple viewpoints and insight from different perspectives, requires a cooperative attitude and open dialogue, and typically leads to consensus and commitment. It may be called problem solve.
[Executing]
4 QUESTION
Describe the difference between ...