Exam Prep Questions

Question 1 The CIO and the head of marketing of a drug development services organization privately discuss a change to a key task in the design phase of a project. After the discussion, they tell the project manager to make the appropriate changes. This scenario is an example of:
  • A. Proactive senior management

  • B. A project-based organization

  • C. Effective decision-making

  • D. A project coordinator role

A1: Answer D is correct. In this scenario, it is the best response. A project coordinator's authority and decision-making ability are generally limited to minor items. Senior management will generally make the significant decisions impacting the scope and success of the project. There is not enough information given to determine whether ...

Get PMP Exam Cram™ 2 now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.