Exam Prep Questions

Question 1 Which of the following must be included in the project charter?
  • A. Risk analysis

  • B. Budget estimates

  • C. Product description

  • D. Scope statement

A1: Answer C is correct. The product description is one of the three requirements of the project charter, as described by the PMBOK. The other alternatives may appear in some organization's charters, but these vary and are not mandated by PMI. Therefore, answers A, B, and D are incorrect.
Question 2 An organization is starting a PMO. For the initial phase, the PMO director has decided to roll out the use of project charters. As a project manager, why would you be encouraged by this plan?
  • A. The project charter allows you to establish the business need for the project.

  • B. The project ...