Exam Prep Questions

Question 1 All the following statements about a WBS are true except which one?
  • A. It provides a framework for organizing and ordering a project's activities.

  • B. It breaks down a project into successively greater detail by level and can be similar in appearance to an organizational chart.

  • C. It's a scheduling method.

  • D. It's a planning tool.

A1: Answer C is correct. A WBS is not a scheduling method. Instead, it provides input into the scheduling process. Therefore, answers A, B, and D are correct.
Question 2 All the following statements are false about the scope statement except which one?
  • A. It provides a documented basis for preparing the PERT/CPM network.

  • B. It's not the basis for the contract between the buyer and seller.

  • C. ...