Exam Prep Questions
Question 1 |
Which of the following statements does not describe what a project plan is?
|
A1: | Answer C is correct. Project plans are used by the entire project team and help to communicate the tasks needed during that timeframe. Project plans are distributed to the project staff according to the communications plan. Further a project plan is formal and approved. Answers A, B, and D are all true statements and are therefore incorrect answers. |
Question 2 |
Which of the following is not true during project execution?
|