Question 1 Which of the following statements does not describe what a project plan is?
  • A. Formal and approved

  • B. A document or collection of documents that change over time

  • C. Only used by the project manager to execute the project

  • D. A method for identifying milestones

A1: Answer C is correct. Project plans are used by the entire project team and help to communicate the tasks needed during that timeframe. Project plans are distributed to the project staff according to the communications plan. Further a project plan is formal and approved. Answers A, B, and D are all true statements and are therefore incorrect answers.
Question 2 Which of the following is not true during project execution?
  • A. The majority of the budget is spent. ...