financially whole, at least for some time (cf. §7.1.8). LDs provide an incen-
tive for the EPC Contractor to take any necessary action to deal with pro-
spective problems. But if the delay extends beyond 6 –12 months, it is likely
that delay LDs will run out, and the pressure on the EPC Contractor then re-
duces considerably.
Unless caused by last-minute performance problems, a delay in reaching
COD by the EPC Contractor is often quite predictable if detailed program-
ming for the project is in place, as it will become evident that critical-path
items (i.e., aspects of the project which, if delayed, will delay the final com-
pletion) are falling behind schedule. The Project Company and the Owner’s
Engineer should be supervising progress sufficiently closely ...