Chapter 30

Resource Loading

Abstract

This chapter describes a manual method for allocating and smoothing resources, if a computer is not available, or for examination purposes, by adding these to the activities of a bar chart (Gantt chart), which was itself created by abstracting the activities and durations from a network. The resources on the bar chart can then be summated for each time period to produce a histogram and the cumulative totals can then be plotted to produce an S-curve, which shows the planned rate of resource usage. The chapter explains that by utilizing the floats, the resources can be smoothed to reduce peaks of resource usage. The relationship between a network, bar chart, histogram and S-curve is shown in one diagram.

Keywords ...