PSP Definitions
Terms Introduced with PSP0
PSP0 Project Plan Summary |
|
Compile Time |
The time from the first compile until the first clean compile |
Test Time |
The time from the start of initial testing until test completion, including defect fix time, recompilation, and so on. |
Defects Removed After Development |
The defects found in the product after development is completed, including all defects subsequently found in testing and use |
To Date |
The cumulative total time, size, or defects for all PSP projects to date. For example, the To Date Test Time is the sum of the testing time for all completed PSP programs to date. |
To Date % |
The distribution of the To Date items among the phases. For defects removed in compiling, the percentage of the ... |