13. Organizational cultures and styles:
A. Are generally similar and manifest in similar ways.
B. Are generally similar but manifest in different ways.
C. Have no impact on a clearly defined project.
D. May have a strong influence on a project's ability to meet its objectives.
14. The project manager has the greatest level of independence and authority in a _______________ organization.
A. Strong matrix
B. Weak matrix
C. Projectized
D. Functional
15. The project manager has the lowest level of authority in a _______________ organization:
A. Functional
B. Weak matrix
C. Strong matrix
D. Projectized
16. A project coordinator may typically be found in a _______________ ...