13.  Organizational cultures and styles:

A. Are generally similar and manifest in similar ways.

B. Are generally similar but manifest in different ways.

C. Have no impact on a clearly defined project.

D. May have a strong influence on a project's ability to meet its objectives.

14.  The project manager has the greatest level of independence and authority in a _______________ organization.

A. Strong matrix

B. Weak matrix

C. Projectized

D. Functional

15.  The project manager has the lowest level of authority in a _______________ organization:

A. Functional

B. Weak matrix

C. Strong matrix

D. Projectized

16.  A project coordinator may typically be found in a _______________ ...