Long description
The rows are filled out, descending, in the following manner:
In row A required date the number 50 appears in week 6.
In row A order release the number 50 appears in week 5.
Lead time for row A equals 1 week.
A note between rows A and B reads “Every part A requires 2 part B’s in week 5.”
In row B required date the number 100 appears in week 5.
In row B order release the number 100 appears in week 3.
Lead time for row B equals 2 weeks.
In row C required date the number 150 appears in week 5.
In row C order release the number 150 appears in week 4.
Lead time for row C equals 1 week.
In row D required date the number 200 appears in week 3.
In row D order release the number 200 appears in week 2.
Lead time for row D equals 1 week. ...