Long description

In the screenshot, the objective is set to “Minimize” using a radio button.

A window titled “Assignments” has a table for the solution of the Fix-it shop. The optimal cost is set to 25 dollars.

  • The column headers are project 1, project 2, and project 3.

  • The row headers are Adams, Brown, and Cooper.

  • Adams’ row has the values: 11, 14, and Assign 6.

  • Brown’s row has the values: 8, Assign 10, and 11.

  • Cooper’s row has the values: Assign 9, 12, and 7.

Get Quantitative Analysis for Management, 13/e now with the O’Reilly learning platform.