Solved Problem 11-1 To complete the wing assembly for an experimental aircraft, Scott DeWitte has laid out the major steps and seven activities involved. These activities have been labeled A through G in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. Determine the expected time and variance for each activity.
| ACTIVITY | a | m | b | IMMEDIATE PREDECESSORS |
|---|---|---|---|---|
| A | 1 | 2 | 3 | — |
| B | 2 | 3 | 4 | — |
| C | 4 | 5 | 6 | A |
| D | 8 | 9 | 10 | B |
| E | 2 | 5 | 8 | C, D |
| F | 4 | 5 | 6 | B |
| G | 1 | 2 | 3 | E |
Although not required for this problem, a diagram of all the activities can be useful. A PERT diagram for the wing assembly is shown in Figure 11.13.