Solved Problems

  1. Solved Problem 11-1 To complete the wing assembly for an experimental aircraft, Scott DeWitte has laid out the major steps and seven activities involved. These activities have been labeled A through G in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. Determine the expected time and variance for each activity.

    ACTIVITY a m b IMMEDIATE PREDECESSORS
    A 1 2 3
    B 2 3 4
    C 4 5 6 A
    D 8 9 10 B
    E 2 5 8 C, D
    F 4 5 6 B
    G 1 2 3 E

    Solution

    Although not required for this problem, a diagram of all the activities can be useful. A PERT diagram for the wing assembly is shown in Figure 11.13.

    Figure 11.13 PERT Diagram for Scott DeWitte (Solved Problem 11-1