Solved Problems
Solved Problem 11-1 To complete the wing assembly for an experimental aircraft, Scott DeWitte has laid out the major steps and seven activities involved. These activities have been labeled A through G in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. Determine the expected time and variance for each activity.
ACTIVITY a m b IMMEDIATE PREDECESSORS A 1 2 3 — B 2 3 4 — C 4 5 6 A D 8 9 10 B E 2 5 8 C, D F 4 5 6 B G 1 2 3 E Solution
Although not required for this problem, a diagram of all the activities can be useful. A PERT diagram for the wing assembly is shown in Figure 11.13.