Solved Problems

  1. Solved Problem 11-1 To complete the wing assembly for an experimental aircraft, Scott DeWitte has laid out the major steps and seven activities involved. These activities have been labeled A through G in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. Determine the expected time and variance for each activity.

    ACTIVITY a m b IMMEDIATE PREDECESSORS
    A 1 2 3
    B 2 3 4
    C 4 5 6 A
    D 8 9 10 B
    E 2 5 8 C, D
    F 4 5 6 B
    G 1 2 3 E

    Solution

    Although not required for this problem, a diagram of all the activities can be useful. A PERT diagram for the wing assembly is shown in Figure 11.13.

    Figure 11.13 PERT Diagram for Scott DeWitte (Solved Problem 11-1

Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.
Start your free trial

You might also like

Quantitative Finance

Quantitative Finance

Maria C. Mariani, Ionut Florescu

Publisher Resources

ISBN: 9780134543161