PREPARATION OF NETWORK WHEN ACTIVITIES ARE GIVEN

Problem 6.42

Draw the network from the following activity and find critical path and total project duration.

 

Activity Immediate Predecessors Duration (Days)
A 10
B 9
C A 9
D A 8
E B 7
F B 11
G D, E 5

Solution

Activities and Duration of Project
Various Paths Duration of Paths
1-2-5 10 + 9 = 19
1-2-4-5 10 + 8 + 5 = 23
1-3-4-5 9 + 7 + 5 = 21
1-3-5 9 + 11 = 20

Hence Critical Path is 1-2-4-5 i.e. (A-D-G) with Project duration of 23 days.

Problem 6.43

Draw the network from the following activity:

 

Activity Immediate Predecessors
A -
B A
C A
D B
E A
F B
G C, D
H F