PREPARATION OF NETWORK WHEN ACTIVITIES ARE GIVEN
Problem 6.42
Draw the network from the following activity and find critical path and total project duration.
Activity | Immediate Predecessors | Duration (Days) |
A | — | 10 |
B | — | 9 |
C | A | 9 |
D | A | 8 |
E | B | 7 |
F | B | 11 |
G | D, E | 5 |
Solution
Various Paths | Duration of Paths |
1-2-5 | 10 + 9 = 19 |
1-2-4-5 | 10 + 8 + 5 = 23 |
1-3-4-5 | 9 + 7 + 5 = 21 |
1-3-5 | 9 + 11 = 20 |
Hence Critical Path is 1-2-4-5 i.e. (A-D-G) with Project duration of 23 days.
Problem 6.43
Draw the network from the following activity:
Activity | Immediate Predecessors |
A | - |
B | A |
C | A |
D | B |
E | A |
F | B |
G | C, D |
H | F |
Get Quantitative Techniques: Theory and Problems now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.