RESOURCE SMOOTHING
Problem 8.22
In the network above are indicated the duration in days and the number of man required for each activity.
You are required:
- To calculate the number of days in which the project can be completed with:
- 5 men
- 6 men
- 7 men
- 8 men
- To find the optimum duration of the project if there is a penalty of Rs. 100 per day if project extends 8 days and the wages per labour is Rs. 100 per day.
Solution
(a) | No. of Men | Days to complete |
5 | 9 | |
6 | 9 | |
7 | 8 | |
8 | 8 |
(b) Calculation of cost
∴ Only 5 men should be ...
Get Quantitative Techniques: Theory and Problems now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.