RESOURCE SMOOTHING

Problem 8.22

PROBLEM 8.22

In the network above are indicated the duration in days and the number of man required for each activity.

You are required:

  1. To calculate the number of days in which the project can be completed with:
    1. 5 men
    2. 6 men
    3. 7 men
    4. 8 men
  2. To find the optimum duration of the project if there is a penalty of Rs. 100 per day if project extends 8 days and the wages per labour is Rs. 100 per day.

Solution

(a) No. of Men Days to complete
  5 9
  6 9
  7 8
  8 8

 

(b) Calculation of cost

Calculation of cost

∴ Only 5 men should be ...