Appendix 8. Answers to Exercises

Chapter 2

(a)(b)
1.1141.1
2.0.990.42 (0.12*)
3.10–510–3
4.2.2×10–30.18 (0.22*)
5.NegligibleNegligible
6.Unavailability×2Unavailability×2
*Beware the approximation. λt is large (i.e. 0.876). Furthermore, if the 10 000 hr per year approximation were used, then λt=1.

Chapter 5

1. Accumulated time T=50×100=5000 hr. Since the test was time truncated n=2(k+1).
Therefore,
(a)n=6, T=5000, α=0.4. From Appendix 2, χ2=6.21
B9780080969022000337/si1.gif is missing
(b)n=2, T=5000, α=0.4. From Appendix 2, χ2=1.83
B9780080969022000337/si2.gif is missing
2. If k=0 then n=2 and since confidence level=90%, α=0.1
Therefore ...