This appendix expands the 5 Content Tab from the 01 ART Readiness Workbook (V6.0) from the SAFe® PI Planning Toolkit.
In the following table, you will see the key activities outlined as well as tasks/activities that are typically executed to meet the overall deliverable. Although the list is not comprehensive, you can use it as a template and refine and enhance each PI for specifics within your organization.
The dates make the following assumptions:
PI event start date |
6/6/23 |
Inspect and Adapt (I&A) date |
6/5/23 |
Number of iterations in PI |
Five |
Innovation and Planning (IP) iteration start date |
5/31/23 |
An additional column is displayed with the formula used to calculate the recommended due dates. The parameters ...