Assigning Resources to Tasks

As discussed in the previous section, the initial assignment schedule is influenced by task settings such as Task Type and Effort Driven, as well as by the choice of assignment units and work. As shown in Chapter 9, you can then customize the initial assignment by delaying its start, splitting the work, assigning overtime, choosing a work contour, and so forth. You can use a variety of views and dialog boxes to assign resources to tasks. They are listed here, with those that give you the most control over the assignment details listed last:

  • You can use the Task table in either the Gantt Chart view or the Task Sheet view to enter assignments in the Resource Names column, but the syntax is strict, and you can specify ...

Get Special Edition Using Microsoft® Project 2002 now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.