1. In a PERT analysis, what is the probability that an activity will be completed no later than the PERT estimate?
(a) 50.00%
(b) 84.13%
(c) 15.87%
(d) 61.79%
2. The triple constraints include:
(a) risk, quality, and procurement.
(b) time, risk, and quality.
(c) time, cost, and quality.
(d) time, cost, and performance.
3. A critical path activity can be compressed from eight ...