APPENDIX BThe Detailed Planning Model

In Chapters 9, 10, and 12, we explored a six‐step model for developing a detailed project plan. The example for this model, the home landscape project, was spread over these three chapters. To make it easier to see the steps of planning, the home landscape project example is repeated here, beginning with the detailed planning model in Figure A.1 and following the stages through to completion (Figures A.2 through A.6).

image

FIGURE A.1 Detailed planning model.

ID Task Name Predecessors Duration Labor Hours Resource Names
1 Design home landscope 5 days 80 hrs. Homeowner [0.5], Teens [1.5]*
2 Put in lawn
3 Acquire lawn materials 1 2 days 64 hrs. Homeowner, Teens [3]
4 Install sprinkler system
5 Identify sprinkler locations 1 1 day Fixed fee, 8 hrs. Contractor, Homeowner
6 Dig trenches 5, 11 2 days Fixed fee Contractor
7 Install pipe and hardware 6 3 days Fixed fee Contractor
8 Cover sprinkler system 7 1 day Fixed fee Contractor
9 Plant grass
10 Remove debris 4 days 256 hrs. Teens [3], Youth Group [5]
11 Prepare soil 10, 3 4 days 96 hrs. Teens [3], Rototiller
12 Plant lawn seed 8 1 day 16 hrs. Teens [2]
13 Plant shrubs 10, 1 6 days 96 hrs. Teens [2]
14 Build fence
15 Acquire fence material 1 2 days 16 hrs. Homeowner
16 Install fence
17 Mark fence line 1 1 day 32 hrs. Homeowner, Teens ...