Chapter 6. Linking the tasks
In this section:
Tasks within a project are often dependent upon one another—for example, the completion date of one task determines when another can start. Tasks linked by a dependency are called either a predecessor task (the driving task) or a successor task (the driven task). These links between tasks are called dependencies, and there are four types: Finish to Start, Start to Start, Finish to Finish, and Start to Finish. The default dependency type is Finish to Start.
Dependency Type | Example | Description |
Finish to Start (FS) dependency | The default dependency type is Finish to Start. The finish ... |