Chapter 6. Linking the tasks

In this section:

Tasks within a project are often dependent upon one another—for example, the completion date of one task determines when another can start. Tasks linked by a dependency are called either a predecessor task (the driving task) or a successor task (the driven task). These links between tasks are called dependencies, and there are four types: Finish to Start, Start to Start, Finish to Finish, and Start to Finish. The default dependency type is Finish to Start.

Dependency Type

Example

Description

Finish to Start (FS) dependency

The default dependency type is Finish to Start. The finish ...

Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.
Start your free trial

You might also like

Microsoft Project 2013: Step by Step

Microsoft Project 2013: Step by Step

Carl Chatfield, Timothy Johnson
Using Microsoft Project 2010

Using Microsoft Project 2010

Brian Kennemer, Sonia Atchison
Microsoft® Project 2010 Inside Out

Microsoft® Project 2010 Inside Out

Teresa S. Stover, Bonnie Biafore, and Andreea Marinescu

Publisher Resources

ISBN: 9780735672888Purchase book