Chapter 10. Practice Exam 1

Question 1 During what phase of the lifecycle is the project scope statement created?
  • A. Concept

  • B. Planning

  • C. Requirements definition

  • D. Feasibility study

Question 2 All the following statements about a WBS are true except which one?
  • A. It provides a framework for organizing and ordering a project's activities.

  • B. It breaks down a project into successively greater detail by level and can be similar in appearance to an organizational chart.

  • C. It's one of the methods available to build a project schedule.

  • D. It's a key project planning tool.

Question 3 During which phase of the project lifecycle is there the greatest degree of uncertainty?
  • A. Initiating

  • B. Planning

  • C. Executing

  • D. Controlling

Question 4 Which project-selection ...