1. B

2. C

3. A

4. A

5. D

6. C

7. D

8. A

9. A

10. D

11. D

12. A

13. C

14. A

15. D

16. D

17. A

18. D

19. A

20. A

21. B

22. A

23. A

24. A

25. C

26. B

27. D

28. A

29. C

30. A

31. A

32. B

33. A

34. A

35. A

36. D

37. A

38. C

39. A

40. D

41. A

42. A

43. A

44. B

45. A

46. C

47. C

48. B

49. B

50. B

Question 1 Answer B is correct. The scope statement is an output of scope planning (5.2 PMBOK), which is part of the overall Planning phase. Answer A is incorrect because concept is another term for initiation. Answers C and D are incorrect because they are not official names of project phases.
Question 2 Answer C is correct. A WBS is not a project scheduling method.
Question 3 Answer A is correct. As a project progresses ...