Chapter 3. Project Planning—Core Processes

Exam Prep Questions

1:

The new CIO for Mega Hard Drive Corporation, Roger Bigbucks, brings John into his office to discuss a new project that has been approved to improve the security access to their corporate systems worldwide. Roger explains the key objectives of the project, general time frame, and business value. The CIO assigns John to be the project manager and ends the meeting. What is the first thing John needs to do?

  • A. Determine who the key stakeholders are and have a kickoff meeting.

  • B. Find out how much money he has to use for the project.

  • C. Order new business cards that show he is the project manager.

  • D. Begin developing the scope definition.

2:

Ed is asked to audit a relatively new project that ...