Answers to the “Do I Know This Already?” Quizzes and Review Questions
1. Answer B is correct. It correctly highlights the two most important attributes of a project per PMI. Answers A and D are common best practices but do not speak to describing a project. Answer C is incorrect because it does not speak to a unique product, and the second part, like Answers A and D, do not describe a project.
2. Answer C is correct. It correctly states the first part of the PMI definition of project management. Answer A seems as though it could be correct and is an example of the trickiness that can be found on the PMP exam, but this is not part of the official definition. Answer B is incorrect because it ...