248.Answer: A.

PMBOK® Guide, page 199, Section 6.4.1.2; and Glossary

Resource requirements. The types and quantities of resources required for each activity in a work package.

249.Answer: B.

PMBOK® Guide, page 19, Section 1.2.4.1; and Glossary

Adaptive life cycle. A project life cycle that is iterative or incremental.

250.Answer: C.

PMBOK® Guide, page 200, Section 6.4.2.2; and Glossary

Analogous estimating. A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

251.Answer: D.

PMBOK® Guide, Glossary

Assumption. A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.

252.Answer: A.

PMBOK® Guide, page ...