Glossary

248.The types and quantities of resources required for each activity in a work package.

A.Resource requirements.

B.Resource breakdown structure.

C.Organizational chart.

D.Resource package.

249.A project life cycle that is iterative or incremental.

A.Waterfall.

B.Adaptive life cycle.

C.Predictive life cycle.

D.Progressive development.

250.Tom, a project manager of a large defense project, is using a technique for estimating the duration of an activity in his project using historical data from a similar activity or project.

A.Bottom-up estimating.

B.Top-down estimating.

C.Analogous estimating.

D.Parametric estimating.

251.Dawn is a project manager in a successful product launch in Silicon Valley. She often comes across factors in the ...