278 Total Quality Management
Work requests from 2001–2003 were reviewed at NTPC and sorted by equipment type.
The counts for equipment that comprised 40 per cent of all maintenance performed at the
plant over the 3-year period are shown in Exhibit 8.1. There are several hundred equipment
types in use at the plant. The benet of this systematic breakdown is a focused review of a
limited number of components. In this case, nine equipment types were involved—isolation
valve, panel, pump, door, fan, motor, pneumatic operator, relief valve and breaker.
Breakdown by Manufacturer and Model
The work requests for a specic equipment type are reviewed ...