Chapter 1

“Do I Know This Already?” Quiz

1. B. A project is temporary, not permanent. A project has a defined start and finish, is unique, and has a stated reason or purpose.

2. A. An organization’s portfolio consists of all of the projects, programs, and operations that it manages in order to reach its strategic objectives.

3. C. The project charter is created during the Initiating phase of the project.

4. D. The work breakdown structure (WBS) is created during the Planning phase of a project.

5. A. Project deliverables are created during the Executing phase of a project.

6. C. The project manager directs quality assurance during the Monitoring and Controlling ...