There are several ways to look at resource assignments. You can switch to a usage view, which shows assignments for each task or assignments for each resource. You can also add a form to your Gantt Chart or other task view and review assignment information in relation to selected tasks.
You can see work assigned to resources in either the Task Usage or Resource Usage views. The Task Usage view shows assignments by tasks (see Figure 7-15). The information for each assignment is rolled up, or summarized, in the row representing the task. To switch to the Task Usage view, click View, Task Usage.
Figure 7-15. The Task Usage view shows task duration as well as assignment work.