When you enter progress information for tasks or assignments, by default, the costs associated with those tasks and assignments are calculated accordingly.
If your assigned work resources (people and equipment) are associated with cost rates or per-use costs, when you enter progress information on their tasks or assignments, not only is actual work calculated, but actual costs are as well.
If you have entered costs for material resources, actual costs are also calculated based on the completion of the task.
If you need to, in the Actual Work field, you can change the value for the material by specifying the amount of material actually used. Material ...