Burndowns can tell us a story about the sprint. Let's take a look at the following burndown example:

One of the things that we want to keep an eye on, as we can see at the beginning of this particular three-week sprint, is that we started with 25 story points, and at the end of the sprint, we didn't quite burn down to zero. There's a little hump in red; this hump is caused by work being added to the sprint once it was already started. It also looks like not much was done in the last two weeks, as no story points were burned, and a lot of the points got finished right at the end of the sprint. These would ...