Chapter 6. Coexistence, migration, and integration 163
11.Check the host responds and switch responds for the new nodes. Run the
verification tests listed in the
PSSP for AIX: Installation and Migration Guide
,
GA22-7347.
6.4.3 S70 Enterprise Server
In this scenario, we have an SP frame with two high nodes and an SP Switch2 in
Cluster 1600. We add one S70 as a SAMI attached node to Cluster 1600.
Hardware considerations
Before you integrate a pSeries p680 or an Enterprise Server 7017-S70, S80, or
S85 into a Cluster 1600, a special SAMI interface (FC 3150, FC 3151) must be
integrated into the machine. This provides the connection to the serial por ...