390 Introduction to the New Mainframe: z/VSE Basics
Because an error correction normally requires the failing part to be on the latest
service level, it should be the goal for preventive service to make sure that the
number of PTFs to apply is kept small to solve a sudden and unexpected defect.
This avoids an extensive upgrade having to be done under pressure.
Preventive service recommendations
Some recommendations are:
Install the latest refresh every 12 months, but not later than 24 months. In
addition, order the newest PSP bucket shortly before upgrading to install the
actual HIPER service as well.
Install the latest RSL every 6 months, but not later than 12 months. As before,
additionally order the newest PSP bucket shortly before upg ...